Current EIAs
Current Environmental Impact Assessments and their status are outlined below.
Last updated – 14 December 2022
wdt_ID | Proponent | Project Name / Type | Status | Detail | Next Step |
---|---|---|---|---|---|
26 | Dart / CIG | ISWMS (ReGen) | Pending Proponent | Proponents are carrying out the works as defined in the agreed Terms of Reference. | Proponents to submit chapters of the Environmental Statement to the EAB for review. |
27 | National Roads Authority | Hutland Road Extension | Pending Proponent | Proponents informed of need for EIA. Proponents have not replied. EIA/Project assumed abandoned. | If project is proposed a third time will be reassessed for need for EIA taking into account any changes to proposal or environmental situation over time. |
28 | National Roads Authority | East-West Arterial (to Frank Sound Road) | Pending Proponent | Proponents advised of EIA from 2005. Following the passage of NCA Proponent required by NCC to carry out EIA in 2016. EIA consultants selected by Proponent in 2022. Consultants now preparing TOR for EAB review. | Draft TOR to be submitted to EAB for review. |
29 | FS Inc. | Brac Marina | Pending Proponent | Proponent voluntarily instigated EIA recognizing it would be of benefit to their project and likely be a national development requirement. EIA consultants selected. | Draft TOR to be submitted to EAB for review. |